Looking towards Horseley Road from Lower Church Lane (Dudley Port) on the afternoon of Thursday 6th February 2025. No track
had yet been laid on the stretch between the Horseley Road stop, just visible under the bridge here, and the point where the
canal crosses the alignment at Dudley Port station. No visible start had been made on the Dudley Port tram stop either.